Is there a way to change the number of days of loaded data using ACSIL? I want to load a new symbol using sc.DataFile, but I also want to change the bar time period and the number days of loaded data at the same time. -BD |
[2013-12-11 18:04:24] |
vegasfoster - Posts: 444 |
I would like this feature too, this way when you change the bar size then you could automatically change the number of days to load as well, e.g. 4 range would load 5 days, but 20 range would load 90 days. :)
|
[2013-12-11 18:46:36] |
N2S - Posts: 15 |
+1
|
[2014-12-03 17:42:57] |
Halir - Posts: 2 |
+1
|
[2014-12-03 21:39:21] |
Sierra Chart Engineering - Posts: 104368 |
We will add this capability.
Sierra Chart Support - Engineering Level Your definitive source for support. Other responses are from users. Try to keep your questions brief and to the point. Be aware of support policy: https://www.sierrachart.com/index.php?l=PostingInformation.php#GeneralInformation For the most reliable, advanced, and zero cost futures order routing, *change* to the Teton service: Sierra Chart Teton Futures Order Routing |
[2014-12-06 01:54:12] |
Sierra Chart Engineering - Posts: 104368 |
This has been added and it will be out in the next release. sc.DaysToLoadInChart Sierra Chart Support - Engineering Level Your definitive source for support. Other responses are from users. Try to keep your questions brief and to the point. Be aware of support policy: https://www.sierrachart.com/index.php?l=PostingInformation.php#GeneralInformation For the most reliable, advanced, and zero cost futures order routing, *change* to the Teton service: Sierra Chart Teton Futures Order Routing Date Time Of Last Edit: 2014-12-06 01:54:29
|