Post From: sc.SetChartStudyInputInt() reverts when used with sc.LastCallToFunction()

[2023-10-22 22:46:49]
Sierra_Chart Engineering - Posts: 17185
Change the study inputs back to the original values when this is true:
sc.IsChartbookBeingSaved

But do not perform a recalculation. And then when this is no longer true, change the inputs back again.

The study which which is checking this variable needs to be set to sc.UpdateAlways to know when the Chartbook saving is complete.
Sierra Chart Support - Engineering Level