With respect to post #11: The only difference between how it worked previously and the latest update is that if the current developing bar goes above the highest value or below the lowest value that has been established by a bar previously, then all of the colors will not update to that new high or low but will stay the same color. The developing bar will then be colored the Range 3 Up/Down color. This is all explained in fifth paragraph the documentation here: Numbers Bars: Calculated Values Background Coloring Logic For the most reliable, advanced, and zero cost futures order routing, use the Teton service: Sierra Chart Teton Futures Order Routing |