[2019-05-10 02:28:24]
Sierra Chart Engineering - Posts: 104368
In this particular case you want to add the Bid and Ask Prices study to the chart and then have Study Subgraph Multiply reference that:
Bid & Ask Prices

In the case when a quote recording suffix is being used, then this affects the OHLC values of the price bars so there is no need to choose anything other than the standard bar values from the Input Data input.