Support Board
Date/Time: Fri, 31 Jan 2025 15:52:30 +0000
Post From: How to use bid/ask prices as input data in studies?
[2019-05-10 02:28:24] |
Sierra Chart Engineering - Posts: 104368 |
In this particular case you want to add the Bid and Ask Prices study to the chart and then have Study Subgraph Multiply reference that: Bid & Ask Prices In the case when a quote recording suffix is being used, then this affects the OHLC values of the price bars so there is no need to choose anything other than the standard bar values from the Input Data input. Sierra Chart Support - Engineering Level Your definitive source for support. Other responses are from users. Try to keep your questions brief and to the point. Be aware of support policy: https://www.sierrachart.com/index.php?l=PostingInformation.php#GeneralInformation For the most reliable, advanced, and zero cost futures order routing, *change* to the Teton service: Sierra Chart Teton Futures Order Routing |